Sunday, 21 June 2026 On track, go-live 12 Sep 2026

Cronulla Pools × Neighbourhood

Where the build is,
and the date it lands.

Your progress report for the HubSpot RevOps Build. Not an ongoing scorecard, a read on how far the project has come and how it tracks against go-live. Every number comes with what it means.

Build progress to go-live

Overall project, complete
0% complete
Go-live target 12 Sep 2026
Schedule Ontrack 0 days slipped
Current phase 2of 5 Build and Configuration
Weeks to go-live 12weeks from today, 21 Jun
What this means. Fifty-eight percent of the build is behind you, and you are on the original go-live date with no slippage. The next milestone is your sign-off on the five build deliverables, which clears the way into Data Migration.

Phase status, five phases

Phase 1 Discovery and Process Mapping Done. Signed off 30 May.
You are here Phase 2 Build and Configuration Pipeline, forms, automation and dashboards being configured in HubSpot. About 65% through.
Approval gate Your sign-off locks scope before Migration
Phase 4 Automation and Training Sequences switched on, your team trained.
Phase 5 Launch and Handover Go-live 12 Sep, then handover.
What this means. One phase done, one in flight. The amber marker is the one decision the project is waiting on you for. Everything after it is sequenced and ready; nothing starts until scope is locked.

Milestones hit so far

Requirements signed off
Phase 1 closed, 30 May
Milestone 1
Five-stage pipeline stood up
Shipped 16 Jun
Milestone 2
Enquiry form auto-creates deals
Shipped 13 Jun
Milestone 3
Reporting dashboards drafted
Shipped 11 Jun
Milestone 4
What this means. Four build checkpoints are in. The next is your sign-off, the gate that turns drafted work into locked scope.

Hours and budget

Hours used, this build 412 of 720
57%
in step with 58% built
Effort spent against the estimate
308hrs
remaining
Estimate left for Build, Migration and Launch
Fixed
price
Scope locks at sign-off, no surprise on the invoice
What this means. Hours spent, 57%, line up with progress built, 58%, so effort is tracking the plan, not running ahead of it. This is a fixed-price project: the hours are how we watch our own pace, not a meter on your bill. New work after sign-off is a separate variation, quoted on its own.
5

Next milestone

5 build deliverables are waiting on your sign-off.

This is the next checkpoint on the progress bar. Accept each one, or request changes. Signing off locks the agreed scope so Data Migration can start, and protects your 12 Sep go-live. Anything new after that is a variation, with its own sign-off and cost.

Review and sign off 1 accepted, 1 in review, 3 pending
Design mockup, illustrative data